Audit of following 2 Work Instructions was done today in Shop # 19. Report is as follows:-

Mounting of Battery and connections ( W 19.024):-
Problems rectified on the spot:-
  • In the loco inspected in test shed, some of the batteries having deficient water indicator float were attended.


  • All the battery terminals found to be sulphated got attended.



  • Main cable ( B006) was of smaller size than the battery connector  cable. Attending this anomaly can reduce the cost.


Mounting of Battery and connections ( W 19.033):-




Observations:-
  • In the batteries of M/S Emco make, electrolyte has to be filled up. This work is prone to dust ingress in the shop.

  • In the batteries of M/S HBLmake, hygrometer probe is not usable.