Audit of
following 2 Work Instructions was done today in Shop # 19. Report is as
follows:-
Mounting
of Battery and connections ( W 19.024):-
Problems rectified on the spot:-
- In the loco inspected in test shed, some of the batteries having deficient water indicator float were attended.
All the battery terminals found to be sulphated got attended.
Main cable ( B006) was of smaller size than the battery connector cable. Attending this anomaly can reduce the cost.
Mounting
of Battery and connections ( W 19.033):-
Observations:-
- In the batteries of M/S Emco make, electrolyte has to be filled up.
This work is prone to dust ingress in the shop.
- In the batteries of M/S HBLmake, hygrometer probe is not usable.