Audit of
following Work Instruction was done in Shop # 19. Report is as follows:-
Assembly
of Roof Equipments And Electrical Connections( W 19.048):-
Quality points:-
- Bolt Tightening work in 3-phase locos can be mechanized as it is
monotonous and voluminous job.
- Quality of welding in the duct welding of OCU should be monitored.
Assembly
Of M/C Room Blower & TM Blower ( WI 19.046)
Quality Cheks:-
Visual only , the impellor mounting on shaft step as mentioned in WI is no more relevant now as blowers are supplied with mounted impellers only.