Sunday, October 14, 2012

How pantographs and filter blocks are assembled?


Audit of following  Work Instructionwas done today in Shop # 19. Report is as follows:-

Mounting of Pantograph assembly ( W 19.025):-
Problem under discussion:-
  • As per WI, pantograph is to be mounted when the roof is on the loco, but most of the time, pantograph mounting is done on the floor only.



  • Fasteners of UNBRAKO make appeared rusty.


Assembly of Filter Block ( W 19.038):-



Discussions:-
  • Some copper connectors appeared discolored.

  • Realignment/re-designing of the mounting of hotel load equipments may reduce the workload.



How Locomotive assembly is done?



Audit of following  Work Instructionwas done today in Shop # 19. Report is as follows:-

Assembly of panel HB1 ( W 19.039):-
  • This work involves precision and should be done in AC environment.

Assembly of panel HB2 ( W 19.037):-
  • This work involves precision and should be done in AC environment.




Mounting of Main Compressor ( WI ( 19.036) 




  •  Both ELGI and Feyvelli MCPs were being fitted in the loco.




Saturday, October 13, 2012

Locomotive Assembly


Audit of following Work Instruction was done in Shop # 19. Report is as follows:-

Assembly of A panel. Preparation of cable of various sizes ( W 19.040):-
Important point:-
  • This work involves precision and should be done in AC environment.


Assembly of C panel . ( W 19.041):-
important point:-
  • This work involves precision and should be done in AC environment.


Assembly of D panel . ( W 19.042):-
  • This work involves precision and should be done in AC environment.

Assembly of F panel . ( W 19.043):-



  • This work involves precision and should be done in AC environment.



Other Issues:-
Equaliser pins of LMS are being cleared by inspection as a temporary measure in order not to hamper production subject to relaxation of hardness.
This needs to be regularized as it cannot continue forever.

Wednesday, October 10, 2012

How 3 phase loco is assembled?


Audit of following Work Instruction was done in Shop # 19. Report is as follows:-

Assembly of Roof Equipments And Electrical Connections( W 19.048):-
Quality points:-

  • Bolt Tightening work in 3-phase locos can be mechanized as it is monotonous and voluminous job.

  • Quality of welding in the duct welding of OCU should be monitored.

Assembly Of M/C Room Blower & TM Blower ( WI 19.046)


Quality Cheks:-





  • Visual only , the impellor mounting on shaft step as mentioned in WI is no more relevant now as blowers are supplied with mounted impellers only.




Thursday, October 4, 2012

Three phase loco manufacturing


Audit of following Work Instruction was done in Shop # 19

Preparation of filter cable( W 19.047):-


 Following issues mentioned in the Railway Boards letter dated 20-01-2012 which were discussed with DyCEE(D&D) again analysed in the the shop :-
  • Use of indigenous hybrid module in WRE gate by BTIL:-


  • Insertion of insulating plate of Fr4 grade Glass Epoxy between gate and cathode plate:



  • Use of Philips IC 74HC T04 in place of Texac make:-only terminals are visible from outside.
  • Modified Heat exchanger:- Modification yet to be confirmed.

  • Stopping use of KUK Make DC link voltage sensor:-LEM make has been discontinued.

All these issues were discussed with the firm as production staff for ensuring quality.