What is to checked in new locomotives to be dispatched ?
HT Cable touching the wall is one such item and should be addressed by a suitably putting a packing
Another NC
observed : absence of sealant in machine room blower pipe which results in air
leakage.
Loco should have no gaps between sheets of cab dashboard which will result in dust
ingress.
All quality
officers should be consulted for checksheet points to be recorded in
register but
in “format’ ; following points could be enlisted:-
1.
Brake
hanger pin check nut in 3-ph loco.
2.
Gap in
between compressor legs and compressor bracket in 3-ph loco.
3.
Dimensional
alignment of vertical damper bracket from loco centre line in 3-ph loco.
4.
Gap measurement
between brake hanger bracket and bogie frame.
5.
Buffer
height and bogie body vertical & lateral/ clearance checking.
6.
Light
passing test to the roof of the shell of locomotives.
7.
Gap in
between central underframe and transformer mounting plate in 3-ph loco.
8.
Standardisation
of permissible waviness in sidewall/ shell to extent of ±6mm.
9.
Rationalising
the standard of pressing force for gear and wheel.
Type of Loco
|
Old standard
|
New standard
|
WAG – 7, WAP – 4
|
Gear: 89 to 117 ton
Wheel: 95 to 132 ton
|
Gear: 95 to 110 ton
Wheel: 100 to 125 ton
|
WAG – 9, WAP – 7
|
Gear: 92 to 104 ton
Wheel: 80 to 102 ton
|
Gear: 95 to 100 ton
Wheel: 85 to 100 ton
|
WAP - 5
|
Gear: 88 to 108 ton
Wheel: 80 to 104 ton
|
Gear: 95 to 105 ton
Wheel: 85 to 100 ton
|
10.
New three check points introduced to measure axial end play
in MSU (motor suspension unit) of wheel sets as per RDSO’s & study.
11.
Extra channel has been introduced in side wall
of WAP-5 locos to reduce waviness.
12.
Standardisation of vibration
and noise level to the extent of 4.5 mm/sec and 110dB to all traction motors
fitted in Bogie Shop of Motorised Bogie.
13.
Air
velocity measurement in machine room for 3-ph locomotives.
14.
Welding
of arch cross member of roof fitment has been modified to arrest rainwater
leakage.
15.
New
template introduced for checking verticality of cab door frame.
16.
New
template introduced for checking compensating and equalising beam of
conventional locos.
17.
Fixture and welding procedure
has been modified to maintain parallelism of two vertical plates during
fabrication of long beam to minimise side deflection in 3-ph locomotives.
18.
Raising the sand box for 3-ph
locomotives. This will reduce the chances of damage of sand box during cattle
run over and ballast hitting.
19.
Additional
BP cock in brake pipe as recommended by RDSO.