Audit of following Work Instructions was done in TM Shop. Report
is as follows:-
Dimensional Check Of Copper Strips and Winding Of Bare Field Coils ( W
21.209):-
Points noticed:-
WI asks for cleaning of guide plate which itself has become rough due to prolonged use. Same should be renewed.
Mandrel for winding preparation INJ-001 and INJ-009 are being sent for calibration.
Bevelling (Milling), Chamfering (Buffing) & Filing Of Bare Field
Coils ( W 21.210-):-
Points noticed:-
Inner radius measurement gauges ING-21.015 and ING-21.016 are being sent for calibration.
Terminal Marking and Cutting ( W 21.211):-
Points noticed:-
- Marking templates are being sent for for calibration.
30 Turn Coil Formation ( W 21.212):-
Points noticed
This WI is no longer relevant since coils received nowadays don’t need cutting.- This WI needs to be delisted.
Other Inspection:-
Problem noticed in TG320 of
MVMT not getting fitted during assembly was inspected in the shop.
Base ring fised in Shop#26 was misaligned due to which MVMT frame went out of alignment. Same was being attended by Shop#26 staff by welding another ring over the top of previously welded ring.